DataBank Red Oak Data Center | Ellis County, TX
DataBank's [Red Oak](/data-centers/texas/ellis/red-oak) campus page describes a 292-acre campus 21 miles south of Dallas, planned for eight two-story data centers. Phase 1 is four buildings and a 400 MW substation delivering up to 300 MW of critical IT power, with Phase 2 bringing the campus to 480 MW across eight buildings. DFW10 is listed at 3330 Batchler Rd., Red Oak, TX 75154, 200,000 IT square feet, 60 MW critical IT load. Data Center Dynamics reported DataBank filings for DFW11 and DFW12 at the Red Oak campus along Stainback Road in Ellis County, two two-story 425,170-square-foot buildings at $325 million each, and that DFW10 construction was set to run from February 2025 to August 2028. TDLR project TABS2026009183 names Databank Red Oak - DFW13, facility DFW13, Stainback Rd, Red Oak, TX 75154, Ellis County, two-story data center with office, 425,170 square feet, start 1 March 2026, completion 31 December 2027, estimated $325 million, owner DB Data Center Red Oak, LLC. Urbanize Dallas later noted DataBank had started construction on the 480 MW Red Oak campus of eight halls. Ellis County also maps Red Oak and [Midlothian](/data-centers/texas/ellis/midlothian); Dallas County maps [GigaPop Red Oak](/data-centers/texas/dallas/gigapop-red-oak) on Stainback Road.
The public map lists 2 buildings. Reported campus capacity is 168 MW. Mix: 1 operating, 1 planned.
Capacity 168 MW reported. Status DFW10 operating; DFW13 planned. City . County Ellis. State TX. Grid .
Buildings
- DataBank Red Oak - DFW10 | 84 MW | operating | 32.53823, -96.73492
- DataBank Red Oak - DFW13 | 84 MW | planned | 32.5385, -96.73965
Related
- Red Oak
- Midlothian
- GigaPop Red Oak
- Stream Wilmer II
- QTS South Dallas DC3
- QTS South Dallas
- PowerCampus Dallas Building 1
- NTT Dallas TX4
- Stream DFW VIII-X
- Stream San Antonio III-VII
- Vantage TX12
- CloudHQ SAT
- Microsoft SAT
- Microsoft SAT11–13
- Microsoft SN7
- QTS San Antonio DC1
- Microsoft SAT Medina
- Rowan Cinco
- ACS Fort Worth
- Aligned DFW03 Mansfield
- CyrusOne DFW7
- Meta Fort Worth
- QTS Fort Worth DC2
- Crusoe Abilene
- Stargate Abilene
- Stargate Frontier
- Stargate Milam
- QTS Turkey
- Meta El Paso
- AWS Comanche Peak
Sources
- Red Oak Campus - DataBank — DataBank, retrieved 2026-09-01
- DataBank files to develop two more data centers at upcoming Red Oak, Texas, campus — Data Center Dynamics, retrieved 2026-09-01
- Databank Red Oak - DFW13 — Texas Department of Licensing and Regulation TABS2026009183, retrieved 2026-09-01
- Powered Lands data center map