PowerCampus Dallas Building 1 Data Center
Dallas County, TX
Project details
Capacity 108 MW reported. Status planned. City . County Dallas. State TX. Grid .
Overview
Data Center Dynamics reported that Skybox Datacenters had started work on the first building of its PowerCampus Dallas site. DCD said the 270,900-square-foot facility was estimated at about $85 million in state planning documents, with delivery anticipated in early 2026, and that PowerCampus Dallas would total 300 MW and 1 million square feet across 115 acres in the Lancaster area of Dallas. Bandera Ventures acquired the site at South Dallas Avenue and Old Red Oak Road, east of Interstate 35E, in April 2023. Dallas Innovates reported the same campus in Lancaster as a partnership of Skybox Datacenters, Bandera Ventures, and Principal Asset Management, up to 300 MW with a private on-site substation and up to 1 million square feet, quoting Skybox CEO Rob Morris on PowerCampus Dallas. Urbanize Dallas placed GigaPop Red Oak 24 miles from this Lancaster campus. The public map lists one planned map record, PowerCampus Dallas - Building 1, at 108 MW. QTS South Dallas, QTS South Dallas DC3, and Stream Wilmer II sit in Wilmer; GigaPop Red Oak, DataBank Red Oak, and Red Oak continue the corridor into Ellis County.
The public map lists one map record, PowerCampus Dallas - Building 1, 108 MW, planned. Reported campus capacity is 108 MW.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- PowerCampus Dallas - Building 1 | 108 MW | planned | 32.56889, -96.76749
Related
- QTS South Dallas 333.9 MW · planned · Dallas
- Stream Wilmer II
- GigaPop Red Oak 540 MW · planned · Dallas
- QTS South Dallas DC3
- NTT Dallas TX4 50.4 MW · planned · Dallas
- Stream DFW VIII-X 90 MW · operating · Dallas
- Red Oak 209.1 MW · Building 1 operating; Building 2 planned · Ellis
- DataBank Red Oak 168 MW · DFW10 operating; DFW13 planned · Ellis
- Midlothian 190 MW · planned · Ellis
- Stream San Antonio III-VII 280 MW · operating · Bexar
- Vantage TX12 96 MW · planned · Bexar
- CloudHQ SAT 720 MW · planned · Bexar
- Microsoft SAT 254 MW · SAT15 operating; SAT16 and SAT17 planned · Bexar
- Microsoft SAT11–13 243 MW · operating · Bexar
- Microsoft SN7 62.5 MW · operating · Bexar
- QTS San Antonio DC1 63 MW · operating · Bexar
- Microsoft SAT Medina 228 MW · operating, planned · Medina
- Rowan Cinco 300 MW · planned · Medina
- ACS Fort Worth 350 MW · planned · Tarrant
- Aligned DFW03 Mansfield 86.4 MW · planned · Tarrant
- CyrusOne DFW7 84 MW · planned · Tarrant
- Meta Fort Worth 105 MW · operating · Tarrant
- QTS Fort Worth DC2 58.8 MW · operating · Tarrant
- Crusoe Abilene 900 MW · planned · Taylor
- Stargate Abilene 1,200 MW · Buildings 1–2 operating; 3–8 planned · Taylor
- Stargate Frontier 1,820 MW · planned · Shackelford
- Stargate Milam 1,200 MW · planned · Milam
- QTS Turkey 999.9 MW · planned · Hall
- Meta El Paso 988 MW · planned · El Paso
- AWS Comanche Peak 715 MW · planned · Somervell
Sources
- Skybox starts work at 300MW data center campus in Dallas, Texas — Data Center Dynamics, retrieved 2026-09-01
- Skybox Datacenters Begins Work on Massive Data Center in Southern Dallas County — Dallas Innovates, retrieved 2026-09-01
- Powered Lands data center map