Stargate Abilene
Taylor County, TX
Project details
Capacity 1200 MW reported. Status Buildings 1–2 operating; 3–8 planned. City Abilene. County Taylor. State TX. Grid ERCOT.
Overview
Stargate Abilene is a data-center campus in Abilene, Taylor County, Texas. It sits immediately north of Crusoe Abilene, in ERCOT.
The campus has eight buildings at 150 MW each. Buildings 1 and 2 are operating. Buildings 3 through 8 are planned. Reported campus capacity is 1,200 MW.
Building 1 is at 32.50512, −99.78102. Building 2 is at 32.50514, −99.77820. Planned Buildings 3 through 8 continue south and west of that pair, still in Taylor County.
Crusoe Abilene sits about a mile south. It has two planned buildings, Building 9 (Microsoft) and Building 10 (Microsoft), at 450 MW each. Crusoe’s reported campus capacity is 900 MW. The ten buildings together are a cluster south of Abilene along Interstate 20.
Abilene is the seat of Taylor County, in west-central Texas.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- Stargate Abilene - Building 1 | 150 MW | operating | 32.50512, -99.78102
- Stargate Abilene - Building 2 | 150 MW | operating | 32.50514, -99.7782
- Stargate Abilene - Building 3 | 150 MW | planned | 32.49899, -99.77673
- Stargate Abilene - Building 4 | 150 MW | planned | 32.49902, -99.77989
- Stargate Abilene - Building 5 | 150 MW | planned | 32.49904, -99.78303
- Stargate Abilene - Building 6 | 150 MW | planned | 32.49906, -99.78619
- Stargate Abilene - Building 7 | 150 MW | planned | 32.49752, -99.7917
- Stargate Abilene - Building 8 | 150 MW | planned | 32.49756, -99.79503
Related
- Crusoe Abilene 900 MW · planned · Taylor
Sources
- Crusoe Announces New 900 MW AI Factory Campus in Abilene, Texas to Support Microsoft AI Infrastructure — Crusoe, March 27, 2026
- Crusoe announces flagship Abilene data center is live — Crusoe, September 30, 2025
- Crusoe to build initial 200 MW AI data center with plans to expand at 1.2 GW Lancium Clean Campus — Crusoe, July 18, 2024
- Stargate Community — OpenAI, January 20, 2026
- Project Radiance expansion on the Lancium Clean Campus — DCOA, March 18, 2025
- Lancium Clean Campus for AI Data Centers: Abilene, Texas — Lancium, accessed August 23, 2026
- Abilene, Texas Data Center — Oracle, January 2026
- Historic Partnership with Lancium for Development of a $2.4 Billion Data Center Campus — City of Abilene / DCOA, December 21, 2021
- Crusoe, Blue Owl Capital, and Primary Digital Infrastructure enter second phase of $15 billion joint venture — Crusoe, May 21, 2025
- 2025 CEDA application for Project Radiance — TEDC
- City Council agenda summary on Lancium phases 1–8 tax abatements — City of Abilene, August 25, 2025
- Powered Lands data center map