AWS Susquehanna
Luzerne County, PA
Project details
Capacity 142 MW reported. Status operating, planned. City . County Luzerne. State PA. Grid .
Overview
AWS Susquehanna is Amazon Web Services’ nuclear-adjacent data-center campus in Luzerne County, Pennsylvania, next to Talen Energy’s Susquehanna Steam Electric Station. Data Center Dynamics reported AWS acquiring Talen’s Cumulus campus for $650 million — $350 million at close and $300 million escrowed against 2024 development milestones — after a Talen investor presentation named Amazon as the buyer. Talen sold the site and assets of Cumulus Data. CEO Mac McFarland said the sale unlocked value from Cumulus and from carbon-free power at Susquehanna. The 1,200-acre campus draws from the neighboring 2.5 GW nuclear station. Talen broke ground in 2021 and completed a first 48 MW, 300,000-square-foot hyperscale hall, with a separate cryptomine remaining with Talen and TeraWulf. Talen said AWS aims to develop a 960 MW campus, with minimum contractual power ramping in 120 MW increments and a one-time option to cap commitments at 480 MW, plus two 10-year extension options tied to nuclear license renewals and a 10-year power-purchase agreement from Susquehanna. Pennsylvania’s other mapped campuses in this directory include Aligned Shippingport, AWS Keystone Trade Center, Panther Creek, PowerHouse PAX-1, Robena, Homer City Energy Campus, and Gouldsboro.
The public map lists 2 map records. Reported campus capacity is 142 MW. Mix: 1 operating, 1 planned.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- AWS Susquehanna - Building 1 | 77 MW | operating | 41.083786, -76.14338
- AWS Susquehanna - Building 4 | 65 MW | planned | 41.080276, -76.14632
Related
- Panther Creek 350 MW · planned · Carbon
- Gouldsboro 1,500 MW · planned · Lackawanna
- Aligned Shippingport 3,600 MW · planned · Beaver
- AWS Keystone Trade Center 252.5 MW · planned · Bucks
- PowerHouse PAX-1 225 MW · planned · Cumberland
- Robena 910 MW · planned · Greene
- Homer City Energy Campus 4,500 MW · planned · Indiana
Sources
- AWS acquires Talen’s nuclear data center campus in Pennsylvania — Data Center Dynamics, retrieved 2026-09-01
- Powered Lands data center map