Helios 1
Dickens County, TX
Project details
Capacity 600 MW reported. Status Helios 1 operating; Helios 2 and Helios 3 planned. City . County Dickens. State TX. Grid .
Overview
Argo Blockchain announced on 5 May 2022 that its Helios facility in Dickens County had been energized, with mining expected to commence the following week. Phase 1 would use 200 MW of power capacity, and Helios had access to up to an additional 600 MW for later phases. Galaxy’s 6 July 2026 newsroom post said it completed delivery of Phase I at the Helios data center campus in West Texas, delivering approximately 200 MW of gross power — 133 MW of critical IT load — to CoreWeave under a 15-year lease, with rent commencement in the second quarter of 2026. Galaxy said greenfield work is underway on 260 MW of critical IT for Phase II, with data-hall deliveries expected in the first half of 2027, that CoreWeave has committed to 526 MW of critical IT across Phases I through III against 800 MW of gross power then approved and contracted, and that the campus spans more than 2,200 acres with approved power expanded to 1.63 GW. Data Center Dynamics reported the same Phase I completion and said Galaxy acquired the campus from Argo in late 2022 for about $65 million after Argo broke ground in July 2021 and started cryptomining in May 2022.
The public map lists 3 map records. Reported campus capacity is 600 MW. Mix: 1 operating, 2 planned.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- Helios 1 | 200 MW | operating | 33.774437, -100.868996
- Helios 2 | 145 MW | planned | 33.777042, -100.868866
- Helios 3 | 255 MW | planned | 33.778385, -100.86887
Related
- Crusoe Abilene 900 MW · planned · Taylor
- Meta El Paso 988 MW · planned · El Paso
- AWS Comanche Peak 715 MW · planned · Somervell
- Qts Turkey 999.9 MW · planned · Hall
- Stargate Milam 1,200 MW · planned · Milam
- Stargate Frontier 1,820 MW · planned · Shackelford
- Stargate Abilene 1,200 MW · Buildings 1–2 operating; 3–8 planned · Taylor
- Stream DFW VIII-X 90 MW · operating · Dallas
Sources
- Energization and Official Opening of Helios Facility — Argo Blockchain, retrieved 2026-09-01
- Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering 133 Megawatts of Critical IT Load to CoreWeave — Galaxy, retrieved 2026-09-01
- Galaxy Digital completes first phase of pivoting cryptomine to AI hosting — Data Center Dynamics, retrieved 2026-09-01
- Powered Lands data center map