George Washington Village
Stafford County, VA
Project details
Capacity 2100 MW reported. Status planned. City . County Stafford. State VA. Grid .
Overview
Garrett Development Corporation is seeking Stafford County approval for a George Washington Village industrial campus of about 7.9 million square feet of data-center and accessory uses on approximately 1,042 acres in the Hartwood District near the Interstate 95 and Courthouse Road interchange. FXBG Advance reported The Garrett Companies requesting rezoning of 20 parcels to M-2 heavy industrial plus a conditional-use permit to raise data-center and transmission or substation height to 105 feet, with attorney Charlie Payne of Hirschler filing a second impact statement and proffer statement in October. Stafford County’s impact statement places the land in the Courthouse and Central Stafford Targeted Development Areas and says full build-out is contemplated over about 20 years, with a voluntary proffer statement limiting uses and offering cash and improvements for public facilities. Stafford County hosts the CUP250109 George Washington Village data-center impact statement and a county data-center planning page for the case. The mapped pin is one planned George Washington Village Data Center building. Vantage VA41 is Stafford County’s other mapped campus, Vantage’s Fredericksburg VA4 park at Centreport Parkway, not this Garrett Hartwood assemblage off Ramoth Church Road. The impact statement’s site-trip analysis treats about 7.842 million square feet of data-center buildings plus accessory uses. This page is the Garrett George Washington Village rezoning, not Vantage’s 82-acre VA4 campus.
The public map lists one map record, George Washington Village Data Center, 2,100 MW, planned. Reported campus capacity is 2,100 MW.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- George Washington Village Data Center | 2100 MW | planned | 38.40892, -77.44693
Related
- Vantage VA41 83.2 MW · planned · Stafford
- Amazon Birchwood 431.4 MW · planned · King George
- Oasis Dahlgren West 1,200 MW · planned · King George
Sources
- GWV- Data Center Impact Statement — Stafford County, retrieved 2026-09-01
- Planning and Zoning | Data Centers — Stafford County, retrieved 2026-09-01
- Developer Seeks Rezoning for 7.9 Million Square Foot Data Center in Stafford — FXBG Advance, retrieved 2026-09-01
- Powered Lands data center map