Capacity 2100 MW reported. Status canceled. City . County Louisa. State VA. Grid .
Overview
Amazon Web Services withdrew plans for a third Louisa County data-center campus on 23 July 2025 after community meetings over light, air, noise, and traffic. Data Center Dynamics reported a letter to county leaders saying AWS would reevaluate the project on land north of the Northeast Creek Reservoir between Davis Highway and Jefferson Highway, near Kennon Road and School Bus Road. Virginia Business said attorney Charles W. Payne, for Amazon, withdrew the conditional-use permit and zoning applications for a 7.2 million-square-foot campus on 1,370 acres in the Mineral area. The campus had been in work since a May 2025 conditional-use filing in the Technology Overlay District, with up to seven substations and buildings at least 850 feet from the nearest residence. AWS already had two Louisa campuses in the overlay: Lake Anna Tech Campus east of Haley Drive and Kentucky Springs Road, filed September 2023 on about 153 acres with up to seven halls totaling 1.7 million square feet, and a November 2024 filing of about 374 acres of ten 382,000-square-foot halls on the other side of Jefferson Highway. Amazon’s 2023 Louisa package promised $11 billion by 2040 for those two parks. Supervisor Duane Adams said the withdrawal showed citizen involvement can slow a filing. County spokesperson Cindy King said newer overlay rules require a conditional-use permit and public input, unlike the earlier by-right halls. EdgeCore Shannon Hill is Louisa County’s other mapped campus, EdgeCore’s Shannon Hill Regional Business Park, not this canceled Amazon third campus.
The public map lists one map record, Louisa County Campus 3, 2,100 MW, canceled. Reported campus capacity is 2,100 MW.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- Louisa County Campus 3 | 2100 MW | canceled | 38.01807, -77.93566
Related
- EdgeCore Shannon Hill 1,100 MW · planned · Louisa
- Mountain Road Technology Park 900 MW · planned · Hanover
- PowerHouse 95 225 MW · planned · Spotsylvania
Sources
- Data Centers in Louisa County — Louisa County, retrieved 2026-09-01
- AWS withdraws plans for third data center campus in Louisa County, Virginia — Data Center Dynamics, retrieved 2026-09-01
- Amazon cancels data center in Louisa County — Virginia Business, retrieved 2026-09-01
- Powered Lands data center map