New Albany Data Center - Socrates South
Licking County, OH
Project details
Capacity 200 MW reported. Status planned. City New Albany. County Licking. State OH. Grid .
Overview
The public map’s New Albany Data Center Socrates South pin is the Morse Road / Beech Road Meta load in Licking County, Ohio, served by Williams’ Socrates South behind-the-meter plant. Data Center Dynamics reported Ohio Power Siting Board approval on June 9, 2025 of the 200 MW Socrates South Power Generation Project, to be built by Will-Power OH, a Williams subsidiary, on the north side of Morse Road just east of Beech Road, with construction slated to start in the third quarter of 2025 and finish in the third quarter of 2026. DCD said the plant will not connect to the grid, that two 24-inch pipelines will supply gas, and that at full build-out Williams planned two 200 MW generation sites costing about $1.6 billion plus a substation for the adjacent data center on Sidecat’s 740-acre New Albany International Business Park campus. The OPSB’s June 9, 2025 release names Sidecat as the offtaker and puts the 20-acre generation pad on that industrial campus where Sidecat already has multiple halls and a latest building under construction next to the plant. The Columbus Dispatch said Socrates South was the first of the two Williams plants approved, with Socrates North then still pending. The public map lists one planned 200 MW map record. OPSB’s June 9, 2025 Socrates South release is the first of the two Williams approvals and names Sidecat’s 740-acre campus as the offtaker. DCD’s Q3 2025 start / Q3 2026 finish is the construction clock for the Morse Road plant next to Meta’s latest hall.
The public map lists one map record, New Albany Data Center - Socrates South, 200 MW, planned. Reported campus capacity is 200 MW.
Map records
Map entries are not a physical building count; campus and building scope may differ across sources.
- New Albany Data Center - Socrates South | 200 MW | planned | 40.054314, -82.75211
Related
- New Albany Data Center - Socrates North 200 MW · planned · Licking
- Meta New Albany 197.6 MW · operating · Licking
- AWS Beech Road 151.2 MW · planned · Licking
- EdgeConneX New Albany 430 MW · planned · Licking
Sources
- Ohio regulators approve construction of 200MW gas power plant to serve Meta's New Albany data center — Data Center Dynamics, retrieved 2026-09-01
- OPSB approves construction of Licking County natural gas-fired power plant — Ohio Power Siting Board, retrieved 2026-09-01
- Ohio Power Siting Board approves Licking County natural gas plant for Meta data center — The Columbus Dispatch, retrieved 2026-09-01